Kastamonu Entegre celebrated the acceptance of its new particleboard plant with Generation 9 ContiRoll® at the Samsun location in Turkey. The entire production range from 6 to 35 m boards was pre-run; the press line produces safely and reliably up to the design speed of 1,200 mm/s. A daily capacity of 2,000 m3 has already been reached.

Maschinen

Siempelkamp installed new particleboard plant for Kastamonu Entegre in Turkey

Siempelkamp installed new particleboard plant for Kastamonu Entegre in Turkey

Bild: Team of Kastamonu Entegre with the first board

Kastamonu Entegre celebrated the acceptance of its new particleboard plant with Generation 9 ContiRoll® at the Samsun location in Turkey.

Start of assembly in July 2020, completed dry run in January 2021, first board at the end of February – on May 1st, the so far most important milestone in the implementation of the project was reached.

KEAS started three-shift operation only 18 days after the first board – one week earlier than scheduled. The nominal output for the main product was achieved shortly after the start of the three-shift operation; due to the excellent know-how of the customer's team, it was already possible to operate with design parameters until acceptance. 

In addition, the entire production range from 6 to 35 m boards was pre-run; the press line produces safely and reliably up to the design speed of 1,200 mm/s. A daily capacity of 2,000 m3 has already been reached.